October DealsAmazon USOctober deal check: compare before you payAmazon US: current deals, useful picks and tech finds.Check DealsSlow PC?RecommendedPC slow today? Run a repair scan before it gets worseResolve common Windows issues and optimize system performance.Scan NowOctober DealsAmazon USDeal season is back - check today's better picksAmazon US: current deals, useful picks and tech finds.See Picks×
Skip to content
World desk4 min

How Long Does a U.S. Aircraft Carrier Overhaul Take? RCOH Explained

A U.S. aircraft carrier’s midlife RCOH is planned for about four years. Here’s what the overhaul includes and why actual schedules can run longer.
Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

A U.S. nuclear aircraft carrier’s midlife Refueling and Complex Overhaul (RCOH) is planned to take about four years, but actual work can take longer. USS George Washington’s maintenance period lasted 2,117 days—nearly six years. RCOH combines reactor refueling with extensive repairs, modernization and testing; it is not simply a refueling stop.

What does RCOH mean?

RCOH stands for Refueling and Complex Overhaul. The U.S. Navy describes it as a carrier’s midlife overhaul, normally around the 25-year point, intended to prepare the ship for the second half of its planned service life. The Navy said in 2021 that USS John C. Stennis’s RCOH was expected to last approximately 48 months and represented about 35 percent of that ship’s lifetime depot-level maintenance. In 2026, the Navy described Truman’s RCOH as nearly one-third of the maintenance and modernization it would receive over a service life exceeding 50 years. Those figures describe the respective ships and Navy estimates; the work package and duration are not identical for every carrier.

As an Amazon Associate I earn from qualifying purchases.

How long does a U.S. aircraft carrier overhaul take?

About four years is a useful planning baseline for an RCOH, not a guaranteed completion time. The elapsed period depends on the ship, its condition and the work required. A completed example shows how much schedules can vary: U.S. Naval Institute News reported that George Washington’s maintenance period lasted 2,117 days, close to six years.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The latest announced case in the cited Navy releases is USS Harry S. Truman. The Navy said on September 29, 2026, that it awarded Newport News Shipbuilding a $5.1 billion fixed-ceiling incentive contract for the overhaul; Truman arrived at the shipyard the next day. The Navy scheduled completion for November 2031, roughly five years after arrival. That is a future target, not a completed result, and the contract’s schedule and price apply to Truman rather than all carrier overhauls. Navy contract announcement.

#1 Best Overall
Metal Earth Premium Series USS Midway Aircraft Carrier 3D Metal Model Kit Fascinations
  • HOBBY MODEL KIT – Unassembled model packed in an envelope with easy to follow instructions. Ideal for ages 14 and up.
  • NO GLUE OR SOLDER NEEDED – Parts can be easily clipped from the metal sheets. Tweezers are the recommended tool for bending and twisting the connection tabs.
  • PREMIUM SERIES USS MIDWAY AIRCRAFT CARRIER - 2 Sheet Model with a challenging difficulty level. Once assembled, dimensions are 8.27 L x 2.24 W x 1.38 H inches. 1:1410 Scale.
  • FROM STEEL SHEETS TO 3D – Pop out the pieces and connect using tabs and holes. Includes illustrated instructions
  • HIGHLY DETAILED ETCHED MODEL – Display your 3D model once completed - collect and build them all.

What work is involved in an RCOH?

The overhaul combines nuclear-plant defueling and refueling with depot-level maintenance, repairs and modernization across the ship. The Navy’s 2026 Truman contract announcement calls it a full recapitalization, including upgrades and repairs to ship systems. Newport News Shipbuilding’s account of Truman’s work lists hull and freeboard blasting and painting; repairs to propellers, sea chests, shafts and rudders; and power-plant defueling and refueling. The Navy’s Stennis account describes disassembly and replacement of surfaces and structures, complex machinery and system repairs or replacement, and propulsion-plant repairs followed by operating tests.

The detailed work package varies with the carrier’s condition and approved requirements. At a high level, the process runs from preparation and offload through refueling, repairs and modernization, then testing and sea trials.

Rank #2
Academy USS Enterprise CVN-65 Aircraft Carrier Plastic Model Kits 1/600 Scale
  • Needs Assembly; Glue is Needed;(Not Included) If you want the same body color of the sample images, paint is needed(Not Included)
  • Includes photo etched radar, ladder, railing, masking seal, tractor, car, aircraft and display stand
  • Includes photo etched radar, ladder, railing, masking seal, tractor, car, aircraft and display stand;"
  • Includes photo etched radar, ladder, railing, masking seal, tractor, car, aircraft and display stand;"

1. Prepare and inspect

Advance planning, long-lead material orders, shipboard inspections and shipyard preparation begin before the main overhaul. The Navy described a Stennis preparation period called “Smart Start,” which included temporary services, removal of decking and catapult equipment, painting and sampling work, and refueling preparations. HII said Truman’s preparation included years of advance planning, long-lead material orders, thousands of inspections and preliminary work.

Free tools Windows power users keep installed

One-click scans. No signup required.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

2. Offload equipment and supplies

During the Shipboard Consolidated Offload and Outfitting Plan, crew members and contractors remove equipment and supplies that are not built into the ship and place them in storage. This clears space and supports access for the shipyard work.

Rank #3
SEMKY Military Series USS Enterprise Aircraft Carriers MOC Building Blocks and Engineering Toy(1883 Pieces)
  • Features: This SEMKY USS Enterprise Aircraft Carriers model has sliding wheels that link the propeller to turn. It truly reflects the sophistication of Military Warship with its clean, modern lines and sculpted surfaces.
  • Giftable:An immersive and rewarding building experience with this highly authentic SEMKY USS Enterprise Aircraft Carriers, packed with realistic features and functions.
  • Function: Wonderful recreation activity, a perfect gift for both adults and ages 10 years up children. Putting this set together with your partner, parent, child or friend and have a keepsake to remember the moment.
  • Exhibitability: The SEMKY USS Enterprise Aircraft Carriers models with incredible detail, astounding authenticity and unparalleled realism. After finish, Collect, Build and Display World Famous Craft in your home, Wonderful 3D art.
  • Note: All pieces in SEMKY products are sorted and packaged by the machine. We can only confirm the packaging after many strict inspections.. If your sets are still missing pieces, please contact us. We will send the missing parts to you for free, thanks in advance.

3. Refuel, repair and modernize

The nuclear plant is defueled and refueled while shipyard teams address propulsion equipment, the hull and underwater components, machinery, and ship systems. Depending on the approved work package, components are repaired, replaced or upgraded. Inspections can also identify additional work after the overhaul is underway.

4. Test the ship before return to sea

Refueling and repairs are followed by operating checks and shipwide testing. The Navy’s Stennis account lists shore steaming, cold and hot operations, power-range testing, a total-ship test program, “fast cruise” and sea trials among the milestones before the carrier resumes operations at sea. These are distinct steps; a ship’s arrival, undocking, sea trials and final redelivery are not interchangeable measures of completion.

Rank #4
Tamiya 31712 1/700 US Aircraft Carrier Yorktown Plastic Model Kit
  • Hanger doors may be depicted in open or closed position
  • Elevator at the stern may be depicted in up or down position
  • 1/700 Scale Warship
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Why do carrier overhauls take so long?

RCOH joins work on a complex nuclear-powered ship with a major refueling effort, so the schedule can change as the ship is inspected and work progresses. USNI News reported several contributors to George Washington’s extended maintenance period: planning and induction delays following earlier budget decisions, a more challenging arrival condition than expected or budgeted that generated growth work, removal of critical parts to support higher-priority deploying carriers, and COVID-19 effects on the workforce and industrial base. Navy reporting on Stennis also cited mandatory growth work identified through ship-condition assessments and industrial-base challenges. USNI News account of George Washington’s maintenance period.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
  • Ship condition and inspection findings: Newly identified repairs can add work beyond the initial plan.
  • Planning and funding: Changes before induction can affect when work starts and how it is organized.
  • Parts and competing fleet needs: Parts may be needed to support other deploying carriers.
  • Shipyard capacity: Workforce and industrial-base constraints can affect the pace of work.

How to interpret an announced completion date

A stated RCOH duration is meaningful only alongside the milestone it measures. A shipyard arrival date marks the start of the period, while undocking, sea trials and final redelivery occur at different points. Truman’s November 2031 date is the Navy’s announced completion target; until the work is finished, it does not establish the actual elapsed duration.

Quick Recap

Bestseller No. 4
Tamiya 31712 1/700 US Aircraft Carrier Yorktown Plastic Model Kit
Tamiya 31712 1/700 US Aircraft Carrier Yorktown Plastic Model Kit
Hanger doors may be depicted in open or closed position; Elevator at the stern may be depicted in up or down position
$29.83
Bestseller No. 5
Tamiya 78007 1/350 USS Enterprise Aircraft Carrier Plastic Model Boat Kit
Tamiya 78007 1/350 USS Enterprise Aircraft Carrier Plastic Model Boat Kit
Highly accurate static display model.; Kit is 38.47 Inch long; Deck-Edge Elevator can be in either up or down position
$173.44
Best Value
Tamiya 78007 1/350 USS Enterprise Aircraft Carrier Plastic Model Boat Kit
  • Highly accurate static display model.
  • Kit is 38.47 Inch long
  • Deck-Edge Elevator can be in either up or down position
  • 1/350 Scale Warship

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

More from the Wire

  1. World desk4 min
    How to Spot an AI Voice Scam Before Sending MoneyDon’t rely on how a caller sounds. Pause, call back through a known number, and verify the emergency with another trusted person before sending money.
  2. Mountain View desk4 min
    Google’s SynthID Detector: How to Check AI-Generated Images, Video and AudioGoogle’s SynthID Detector looks for an embedded watermark in supported images, video and audio. Here is what its results do—and do not—show.
  3. Redmond desk20 min
    How to create a link to File or Folder in Windows 11Windows 11 gives you several ways to point to a file or folder without moving or duplicating it. You can create a desktop shortcut,…
Recommended PC Tool
Recommended PC Tool
PC Slower Than It Used to Be?Free scan - under a minute
Outdated Drivers Are Slowing You DownFree scan - exact matches

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.