October DealsAmazon USOctober deal check: compare before you payAmazon US: current deals, useful picks and tech finds.Check DealsSlow PC?RecommendedPC slow today? Run a repair scan before it gets worseResolve common Windows issues and optimize system performance.Scan NowOctober DealsAmazon USDeal season is back - check today's better picksAmazon US: current deals, useful picks and tech finds.See Picks×
Skip to content
World desk4 min

How a Nuclear-Powered Aircraft Carrier Refueling Overhaul Works

A carrier RCOH is a multi-year shipyard project that combines reactor refueling with major repairs, modernization, installation and staged testing before sea trials.
Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

A U.S. Navy carrier’s midlife refueling overhaul—called a Refueling and Complex Overhaul, or RCOH—is a years-long shipyard project, not a routine refueling stop. The Navy refuels the reactors while the ship undergoes major repairs and modernization across propulsion, electronic, combat-support and other ship systems. The crew and shipyard then install equipment, test the ship in stages and conduct sea trials before it returns to the fleet.

What an RCOH is—and why it takes years

An RCOH combines reactor refueling with extensive repair and modernization so a carrier can serve the latter part of its planned life. Propulsion is central, but the work is not limited to the reactors: the Navy describes upgrades to propulsion equipment, infrastructure and electronic systems, along with work on broader ship and combat-support capabilities.

As an Amazon Associate I earn from qualifying purchases.

The project is undertaken by the ship’s crew, Newport News Shipbuilding and other contractors. It involves intrusive work that requires the carrier to be in the shipyard, including a period in dry dock, followed by outfitting and testing. The precise work package and sequence vary by ship; published accounts of individual carriers are examples, not a fixed checklist for every RCOH.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

How the overhaul proceeds

1. Plan, inspect and prepare

Planning and preparation begin well before the main shipyard work. For USS John C. Stennis, the Navy described a preparatory period called “Smart Start,” alongside inspections, long-lead procurement and facility preparation. That ship’s preparations included setting up temporary services and systems, removing decking and catapult equipment, and sampling paint, lagging and tile. Its Shipboard Consolidated Offload and Outfitting Plan (SCOOP) removed equipment, tools and other items not built into the ship for storage.

#1 Best Overall
Metal Earth Premium Series USS Midway Aircraft Carrier 3D Metal Model Kit Fascinations
  • HOBBY MODEL KIT – Unassembled model packed in an envelope with easy to follow instructions. Ideal for ages 14 and up.
  • NO GLUE OR SOLDER NEEDED – Parts can be easily clipped from the metal sheets. Tweezers are the recommended tool for bending and twisting the connection tabs.
  • PREMIUM SERIES USS MIDWAY AIRCRAFT CARRIER - 2 Sheet Model with a challenging difficulty level. Once assembled, dimensions are 8.27 L x 2.24 W x 1.38 H inches. 1:1410 Scale.
  • FROM STEEL SHEETS TO 3D – Pop out the pieces and connect using tabs and holes. Includes illustrated instructions
  • HIGHLY DETAILED ETCHED MODEL – Display your 3D model once completed - collect and build them all.

These details show the kinds of work preparation can involve; they should not be read as a universal RCOH checklist. The Navy has also described dedicated facilities for organizing overhaul work: in June 2026, it reported the opening of a Carrier Refueling Overhaul Workcenter near the RCOH dry dock, with approximately 80,000 square feet of dedicated space.

2. Move into the shipyard and complete the heavy work

The carrier transits to the shipyard and enters dry dock for work that cannot be carried out during ordinary operations. Reactor refueling takes place as part of this phase, alongside repairs and upgrades to the propulsion plant and work throughout the ship. Public Navy accounts describe the purpose and broad scope, but do not provide a procedural account of reactor defueling, fuel handling, radiological controls or detailed nuclear-plant work instructions. Those technical steps should not be inferred from the general description of an RCOH.

Rank #2
Academy USS Enterprise CVN-65 Aircraft Carrier Plastic Model Kits 1/600 Scale
  • Needs Assembly; Glue is Needed;(Not Included) If you want the same body color of the sample images, paint is needed(Not Included)
  • Includes photo etched radar, ladder, railing, masking seal, tractor, car, aircraft and display stand
  • Includes photo etched radar, ladder, railing, masking seal, tractor, car, aircraft and display stand;"
  • Includes photo etched radar, ladder, railing, masking seal, tractor, car, aircraft and display stand;"

3. Leave dry dock for outfitting

Dry-dock work is not the finish line. In July 2024, the Navy reported that Stennis had undocked in April and would move to an outfitting berth for further installation and testing of major components and combat-support systems. This transition lets the project continue with equipment installation and ship-wide work after the dry-dock period.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

4. Test the ship, then conduct sea trials

Testing checks the propulsion plant and other systems as the overhaul progresses toward return to service. The Navy’s Stennis account lists shore steaming, cold and hot operations, and power-range tests, followed by total-ship testing, fast cruise and sea trials. Fast cruise is named as a milestone in that ship’s account; the public description does not establish detailed criteria or a universal sequence for every carrier.

Rank #3
SEMKY Military Series USS Enterprise Aircraft Carriers MOC Building Blocks and Engineering Toy(1883 Pieces)
  • Features: This SEMKY USS Enterprise Aircraft Carriers model has sliding wheels that link the propeller to turn. It truly reflects the sophistication of Military Warship with its clean, modern lines and sculpted surfaces.
  • Giftable:An immersive and rewarding building experience with this highly authentic SEMKY USS Enterprise Aircraft Carriers, packed with realistic features and functions.
  • Function: Wonderful recreation activity, a perfect gift for both adults and ages 10 years up children. Putting this set together with your partner, parent, child or friend and have a keepsake to remember the moment.
  • Exhibitability: The SEMKY USS Enterprise Aircraft Carriers models with incredible detail, astounding authenticity and unparalleled realism. After finish, Collect, Build and Display World Famous Craft in your home, Wonderful 3D art.
  • Note: All pieces in SEMKY products are sorted and packaged by the machine. We can only confirm the packaging after many strict inspections.. If your sets are still missing pieces, please contact us. We will send the missing parts to you for free, thanks in advance.

Sea trials provide an at-sea opportunity to exercise the ship after the shipyard work. In its May 2023 account of USS George Washington’s RCOH completion, Naval Sea Systems Command said trials tested the full range of operating systems and included high-speed maneuvering evolutions intended to stress new technology and equipment. That is a published example, not proof that every ship’s trials use identical events.

What published carrier examples show about schedules

These dated reports illustrate how an RCOH can span multiple years. Forecasts and status updates below belong to the report dates shown; they are not confirmation of later completion.

Rank #4
Tamiya 31712 1/700 US Aircraft Carrier Yorktown Plastic Model Kit
  • Hanger doors may be depicted in open or closed position
  • Elevator at the stern may be depicted in up or down position
  • 1/700 Scale Warship
Carrier Published milestone What the report establishes
USS John C. Stennis (CVN 74) Navy reports from May 2021 and July 2024 Stennis transited to Newport News for RCOH in May 2021. In July 2024, the Navy said the ship was more than 65 percent complete and tracking for redelivery in October 2026; that was a target reported at the time, not a verified October 2026 outcome.
USS George Washington (CVN 73) Naval Sea Systems Command report, May 2023 The Navy reported RCOH completion and described sea trials that tested operating systems and included high-speed maneuvering.
USS Harry S. Truman (CVN 75) Navy contract announcement, September 2026 The Navy announced a $5.1 billion fixed-ceiling incentive contract for Truman’s RCOH and scheduled completion for November 2031. The ship was delivered in 1998. The completion date is a forecast in the announcement, not a confirmed result.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

How much work is involved?

RCOH requires substantial effort from both shipyard workers and the ship’s crew. A May 2020 Navy report said USS George Washington’s ship’s force had completed more than 1.3 million work-hours out of 2,306,996 planned work-hours for that carrier’s specific RCOH. Those figures describe that ship’s work package; they are not a standard labor estimate for all carriers.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

The numbers and milestones help convey the scale, but they do not make every overhaul directly comparable. Each ship’s scope and schedule are specific to its project, and a reported target should not be mistaken for an actual redelivery date.

Quick Recap

Bestseller No. 4
Tamiya 31712 1/700 US Aircraft Carrier Yorktown Plastic Model Kit
Tamiya 31712 1/700 US Aircraft Carrier Yorktown Plastic Model Kit
Hanger doors may be depicted in open or closed position; Elevator at the stern may be depicted in up or down position
$29.83
Bestseller No. 5
Tamiya 78007 1/350 USS Enterprise Aircraft Carrier Plastic Model Boat Kit
Tamiya 78007 1/350 USS Enterprise Aircraft Carrier Plastic Model Boat Kit
Highly accurate static display model.; Kit is 38.47 Inch long; Deck-Edge Elevator can be in either up or down position
$173.44
Best Value
Tamiya 78007 1/350 USS Enterprise Aircraft Carrier Plastic Model Boat Kit
  • Highly accurate static display model.
  • Kit is 38.47 Inch long
  • Deck-Edge Elevator can be in either up or down position
  • 1/350 Scale Warship

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

More from the Wire

  1. World desk4 min
    How to Spot an AI Voice Scam Before Sending MoneyDon’t rely on how a caller sounds. Pause, call back through a known number, and verify the emergency with another trusted person before sending money.
  2. Mountain View desk4 min
    Google’s SynthID Detector: How to Check AI-Generated Images, Video and AudioGoogle’s SynthID Detector looks for an embedded watermark in supported images, video and audio. Here is what its results do—and do not—show.
  3. Redmond desk20 min
    How to create a link to File or Folder in Windows 11Windows 11 gives you several ways to point to a file or folder without moving or duplicating it. You can create a desktop shortcut,…
Recommended PC Tool
Recommended PC Tool
PC Slower Than It Used to Be?Free scan - under a minute
Outdated Drivers Are Slowing You DownFree scan - exact matches

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.