China’s Lufeng Nuclear Power Station reached two separately reported milestones in October 2026: welding of the main nuclear-island pipelines at Unit 6 was completed on 28 September, while a pressuriser was installed at Unit 1. The activities show different stages of work on individual reactors, not completion of the six-reactor station.
What was announced in October 2026
NucNet reported on 13 October 2026 that the main pipeline welding inside Lufeng Unit 6’s nuclear island had been completed on 28 September. The report said this work lays the basis for nuclear-loop flushing and cold hydraulic testing, which are subsequent testing activities. It did not describe Unit 6 as complete or operational.
As an Amazon Associate I earn from qualifying purchases.
The same report identified pressuriser installation at Unit 1 as another milestone. Because the report does not give a separate installation date, it should be treated as a current project update rather than assigned an unsupported event date. The Unit 1 and Unit 6 developments are distinct and should not be combined into a single station-wide progress figure.
Quick wins for a faster PC:
Repair Windows errors before they cause bigger problemsFix Now →Scan for outdated or missing drivers - takes under a minuteDriver Scan →Clear out junk files and repair common Windows errorsFree Scan →How the six units compare
The available announcements cover different kinds of work, so a dome hoist, structural-module placement, pipeline welding and a functional test are not interchangeable measures of progress. The useful comparison is the milestone, its date and what it enables next.
#1 Best Overall
- ATMOSPHERE-BOOSTING HUMIDIFIER MORE THAN JUST MIST: Bring your space to life with a soft green glow and fine ultrasonic mist. This USB-powered humidifier doesn't just add moisture - it creates a calm, immersive atmosphere for bedrooms, desks, or late-night work sessions
- USB POWERED FOR EASY USE ANYWHERE: No bulky setup needed. Simply plug into your laptop, power bank, or adapter and enjoy instant mist anytime. Suitable for office desks, gaming setups, travel, or small personal spaces
- COMPACT SIZE FOR DESKTOP SPACES: Designed to fit seamlessly into your workspace without taking up room. Whether placed beside your monitor, bedside, or shelf, it adds both function and visual appeal without clutter
- SOFT GREEN LIGHT FOR RELAXING AMBIENCE: The built-in green LED light enhances the overall mood, making it suitable for stress relief, relaxation, or creating a unique aesthetic setup. Works well for night use without being too harsh on the eyes
- HUMIDIFIER AND DECOR IN ONE UNIQUE PIECE: Not just a humidifier - a conversation-starting decor piece. Combines practical air moisture benefits with a visually striking design, making it a thoughtful gift or personal setup upgrade
| Unit | Milestone | Date | What it indicates |
|---|---|---|---|
| Unit 6 | Main nuclear-island pipeline welding completed | 28 September 2026 | Prepares the unit for nuclear-loop flushing and cold hydraulic testing |
| Unit 1 | Pressuriser installed | Reported 13 October 2026; installation date not stated | Shows continuing equipment installation in the reactor system |
| Unit 1 | CA03 nuclear-island module hoisted | 23 January 2026 | Earlier structural and equipment-installation progress |
| Unit 2 | Steel containment-vessel bottom head positioned at the reactor-building raft foundation | 6 February 2026 | Progress on containment and reactor-building assembly |
| Unit 5 | Cold functional test completed | 27 April 2026 | Commissioning-stage testing; not evidence that the whole station is operating |
Unit 6: from dome hoisting to pipeline testing
China General Nuclear reported that the Unit 6 reactor-building dome was hoisted on 14 July 2025. The company described that event as marking the transition from civil construction to equipment installation. The later pipeline-welding completion is a different, more advanced system-installation milestone.
Pipeline welding in the nuclear island is followed by activities that verify system cleanliness, integrity and hydraulic performance. At Lufeng, the reported sequence is loop flushing followed by cold hydraulic testing. These are performed without reactor operation and should not be read as fuel loading, grid connection or commercial service.
Rank #2
- A premium display model for adult collectors and history enthusiasts, featuring high-precision 3D printing with metallic luster material. The intricate components can be detached to showcase the remarkable engineering and realistic textured details.
- Designed as an educational tool to demonstrate complex geometric principles. Explore the iconic Fullerene structure (a truncated icosahedron) through this model, which represents a pivotal design from a significant historical scientific project.
- Features a modular design where each polyhedron component can be freely assembled and rearranged into various spatial configurations. This hands-on process provides an engaging and thoughtful exploration of structural mechanics and is ideal for STEM learning.
- Serves as a sophisticated conversation piece for office or study desk decor. It makes a unique and thoughtful gift for avid collectors, physics buffs, military history aficionados, or anyone who appreciates precision models and scientific history.
- Crafted for long-term display with stunning visual impact and fade-resistant quality. THIS IS A COLLECTOR-GRADE, HISTORICAL REPLICA MODEL INTENDED FOR ADULTS. IT IS FOR DISPLAY AND EDUCATIONAL PURPOSES ONLY.
Unit 1 and Unit 2 construction context
Unit 1
CGN said the CA03 module for Unit 1’s nuclear island was hoisted into place on 23 January 2026. Pressuriser installation, reported later in October, represents another equipment milestone, but the available announcement does not provide a percentage complete or a complete schedule for the unit.
Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchWindows Errors? Fix Them Before They Spread
Repair common Windows errors and clear accumulated junk for a smoother, more stable PC - no reinstall needed.Free scan · no reinstallUnit 2
On 6 February 2026, CGN reported positioning the steel containment-vessel bottom head at the center of Unit 2’s reactor-building raft foundation. This is a foundation and containment-assembly step. It cannot be compared directly with Unit 6’s completed welding or Unit 5’s functional test.
Rank #3
- Visualize Molecular: The molecular model kit simplifies complex chemistry concepts into tangible 3D structures improve learning efficiency, suitable for students from Grade 7 to Graduate level.
- 444 Pcs Complete Set: The atom model kit includes with 136 atoms,158 bonds, and 150 fullerene model parts, explore most the molecules structures from simple compounds to complex polymers.
- Effortless Assembly: Embedded component design ensures easy to construct Ball-and-stick and Space-filling models that maximizes focus on exploration without complex assembly.
- Durable & Portable: Built to last, the chemistry set is crafted from high-quality materials. Plus, its portable Snap-Lock design allows you to take your experiments learning anywhere, between the home, classroom and lab.
- Essential Study Tool: Whether you're studying organic chemistry, biochemistry, or molecular biology, molecule building kit is an perfect learning tool for you deeper comprehension of molecular science.
Unit 5 has reached testing, not station-wide operation
CGN reported that Unit 5 completed its cold functional test on 27 April 2026. The company said inspectors examined the unit at a maximum pressure platform of 223 bar.g on 26 April. A cold functional test checks relevant systems under pressure and without normal reactor operating conditions.
That result is a commissioning milestone for Unit 5 only. It does not mean all six planned reactors are commissioned, and it does not establish that Lufeng is producing electricity commercially.
Rank #4
- RTR Version Stirling Engine Model: No need to assemble, unpack the engine model and get ready to see the wonders of science. Comes with a USB LED lights for you to DIY and experience more fun.This is a very interesting and imaginative toy! It can be used for teaching physics, great to display basic principles of a Stirling engine and to show the art of design.
- Good Look Stirling Engine Mode: The bottom of the model is made of high-quality steel, and the bracket is made of aluminum alloy. The bottom of the bracket is wide, stable and solid, exquisite. Due to the heat of alcohol, the engine will run wildly and generate electricity. The power supply will pass through the wire and drive the LED light. Sturdy and durable metal components ensure long operation, enjoy physical powertrain mechanism display.
- Easy to Operate: Fill the alcohol burner with your 95% medical-alcohol (we recommend this fuel) and light it. Let the light burn the cylinder with the rounded ends for about 60 seconds, then gently push the wheel.
- Superior performance: The Stirling engine is equipped with an LED. As power will pass through the wire and turn on the LED light. When the model continues to rotate, the speed is high, the performance is stable, and the rotation can be maintained for a long time.
- Great Educational Tool: This is an amazing and wonderful Stirling Engine, which has a wide range of applications, such as science project, physics / mechanical learning, teacher presentation props in class, friends, family, parents birthday gifts, etc.
When are the reactors expected to operate?
CGN Power’s 2025 annual report listed expected operation in 2027 for Unit 5, 2028 for Unit 6, and 2030 for Units 1 and 2. These are company forecasts, not guaranteed dates or a new confirmation that each reactor will meet its target.
The same filing warns that delivery delays, higher equipment or material costs, regulatory approvals, engineering or environmental issues, and changing safety requirements could affect construction. Actual operation dates may therefore differ from the years in the report.
Best Value
- Educational toys - Through this DIY package, children can exercise their own hands, thinking, exploring, creating ability,Build a toy that light up the LED by hand and the drive motor to learn the principle of conversion between energies.
- Hands on fun - The Hand Cranked Power Generator sets come with complete accessories ,tools and instruction manuals,kids can learn to solve and think about issue while reading the manuals.
- Learn through playing - Kids will learn from the mechanics of the hand-crank generator and how the kinetic energy is used to generate electricity. The Dynamo Lantern is a safe and interactive experience that keeps kids engaged, which makes it one of the most unique electricity learning toys available.
- Safe to play - A great and practical gift for children to enjoy and learn. Popular among schools and teachers for an interactive, hands-on learning experience as well as being one of the safest electricity learning toys in the classroom. Our kids STEM toys contain small parts, not for children under the age of 3.
What is known about the overall project?
NucNet describes Lufeng as a six-reactor project in Guangdong, southern China. The information available for this update does not establish a complete unit-by-unit reactor-design breakdown, total capacity, overall construction percentage, workforce, project cost or a single station completion date. Those figures should not be inferred from the individual milestones.
What the latest progress means
The October announcement confirms parallel progress: Unit 6 is preparing for system flushing and cold hydraulic tests, while Unit 1 is still receiving major equipment. Unit 5 is further along in commissioning tests, and Units 1 and 2 remain on the longer construction path reflected in CGN Power’s forecast operation year of 2030. The station’s status is therefore best understood unit by unit, rather than as one completed project.
Quick Recap
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.
Do these 3 things before closing this tab:
1Clear out junk files and repair common Windows errors2Fix the driver behind crashes, sound loss and screen glitches3Repair Windows errors before they cause bigger problems