There is no single price for an AI data center: a shell-and-core building, a powered and cooled facility, and a fully equipped AI compute deployment have very different costs. JLL forecasts an average global shell-and-core construction cost of $11.3 million per MW in 2026, excluding land and active IT equipment. At a much larger scale, Epoch AI’s stylized model of a 1-GW U.S. hyperscaler facility estimates $37.883 billion in upfront capital expenditure and $907 million in annual operating expenses. These are benchmarks with different scopes, not project quotes.
What does an AI data center cost per MW?
The answer depends first on what the estimate includes. Shell-and-core construction does not buy the GPUs and servers that perform AI workloads; a fully equipped estimate may include those systems, networking, cooling, and other infrastructure. A per-MW figure is useful only when the capacity basis and cost boundary match.
As an Amazon Associate I earn from qualifying purchases.
| Estimate | Cost per MW | Scope and qualification |
|---|---|---|
| JLL global average, 2026 | $11.3 million | Forecast shell-and-core construction cost; excludes land and active IT equipment. JLL models a single-tenant, 50-MW air-cooled facility. |
| JLL selected markets, 2026 | Chicago: $12–14 million; Northern Virginia: $11–12 million; Dallas: $10–11 million; Tokyo: $14–18 million; Mumbai: $6–7 million | Shell-and-core ranges under the same modeled 50-MW air-cooled facility assumptions; excludes land and active IT equipment. |
| Morgan Stanley Research AI data-center build estimate | $21–31 million including GPUs and servers; about $8–14 million excluding them | Analyst estimates; scope differs from JLL’s shell-and-core forecast. |
| JLL AI technology fit-out | Up to $25 million | Upper figure per MW for AI technology fit-out in JLL’s 2026 outlook; not a shell-and-core price. |
These figures should not be added together as if they were components of one quote: their methods and boundaries differ. They do show why a shell-only cost can substantially understate the investment needed for an operational AI deployment.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Cooling and building design change the comparison
In JLL’s assumptions, liquid-cooled facilities carry a 10% construction premium; multistory facilities in the Americas can add 20% to construction costs. Those adjustments relate to JLL’s construction assumptions, not a universal surcharge for every project.
#1 Best Overall
- Space Saving: Maximum depth: 14.8". Use the wall mount network cabinet to maximize available space for retail locations, classrooms, back offices, network cabinets, and other locations where space is limited.
- Fast Heat Dissipation: The server cabinet is designed with vents to optimize airflow and avoid critical IT equipment overheating. Heat sink holes in the top, bottom, and rear panels are more conducive to heat dissipation.
- Sturdy Construction: Robust welded frame construction for durability and long service life. With 100 lbs wall-mounted load capacity and 200 lbs ground-mounted load capacity, you can place multiple devices in the server rack cabinet as needed.
- High Security: The locked glass door ensures the security of data and equipment. Wall mount rack enclosure server cabinet is ideal for use in public places such as offices, effectively protecting the security of your devices.
- Hassle-free Installation: Fully adjustable square-hole mounting rails of the wall mount server cabinet facilitate device installation. Wiring holes on the top, bottom, and rear panels provide you with easy cable routing.
What is included in a 1-GW AI data center estimate?
Epoch AI’s 2026 model offers a more complete, but explicitly stylized, example: a U.S. hyperscaler-owned and operated facility with 1 GW of IT nameplate capacity. It estimates upfront capital expenditure at $37.883 billion.
| Capital category | Modeled upfront cost |
|---|---|
| Servers | $21.188 billion |
| Facility costs | $11.433 billion |
| Network infrastructure | $4.925 billion |
| Land | $172 million |
| Utility works | $164 million |
| Total | $37.883 billion |
The model’s large server and network components illustrate why “building cost” can mean more than construction. Actual totals depend on server choices, facility design, location, financing, and power strategy; the modeled result is not a quote for another site.
Rank #2
- Data Storage Solution: This 12U mobile server cart contains 4 vertical support rails for servers, UPS's, patch panels, switches, and other networking or AV equipment. Product has a length of 23.5" and a height of 28.3"
- Adjustable Depth: The rack features a depth range of 22" to 40" to accommodate the size of your equipment with precise 1" adjustment settings. Provides plenty of space while easily fitting into utility and server closets
- Sturdy Open Frame Design: Extend the life of your valuable equipment by giving it maximum airflow and ventilation for sufficient cooling. Solid steel construction supports up to 1200 lbs of weight with ease
- Smooth Mobility: Four durable casters provide nearly effortless motion for a variety of floor types, and optional leveling feet are included to make the cart stationary when desired
- Simple Assembly: All hardware and step-by-step instructions are provided to get your new server rack assembled in no time
How much does it cost to run an AI data center each year?
Epoch AI estimates annual operating expenses of $907 million for its same 1-GW scenario. Energy is the largest listed operating item, but it is not the only one.
| Annual operating category | Modeled cost |
|---|---|
| Energy | $594 million |
| Taxes | $143 million |
| Maintenance | $120 million |
| Labor | $40 million |
| Water | $6 million |
| Total | $907 million |
The energy estimate uses an assumed electricity price of 8.34 cents per kWh, derived by weighting 2024 U.S. state industrial electricity costs by project counts. The model also assumes a power usage effectiveness (PUE) of 1.14 and 71% utilization. The 8.34-cent figure is a model input based on 2024 data, not a current tariff or a forecast bill for an arbitrary site.
Rank #3
- 24-Bay 12Gbps Storage Powerhouse in 4U: Maximize your rack space efficiency with a petabyte-scale storage server. This chassis is designed for data-intensive environments where high bandwidth and massive capacity are paramount
- Flagship E-ATX Compatibility for Demanding Workloads: Supports the largest E-ATX server motherboards, enabling builds with maximum CPU core count, vast RAM capacity, and extensive PCIe expansion for the most demanding computational workloads
- Enterprise-Grade, Serviceable Cooling System: 3 Hot-Swap 120x38mm fans delivers high-static pressure to cool components effectively. The hot-swap capability guarantees that cooling integrity is never compromised, even during fan maintenance
- Supports 2 x 2U redundant PSU in a standard CRPS cage
Why annual operating expense is not the full annual cost
Operating expense covers ongoing costs such as power, taxes, maintenance, labor, and water. Epoch AI separately annualizes the modeled capital investment over assumed asset lives and estimates total cost of ownership at $8.5 billion per year. In its breakdown, servers account for about 60% of that annualized total. This lifecycle measure should not be confused with the $907 million operating-expense estimate.
Replacement timing changes the annualized result substantially. Epoch assumes a five-year life for IT equipment and a 14-year life for the facility. With IT equipment lasting three years, its modeled annual total cost rises to $12 billion; with a seven-year life, it falls to $7 billion. Comparisons of lifecycle cost therefore need to state the assumed hardware refresh cycle.
Rank #4
- Sturdy:4u server rack is construct from cold rolled steel, with a weight capacity of 110lbs(50kg); Electrostatic powder coat prevents rust and corrosion,quality finish
- Direct use:Open and use, not having to assemble it.Network rack can be placed flat or mounted on the wall,also can be installed vertically under the table
- Design Features:maximum mounting depth of 14 in,cables can be fixed on the side panel;Open frame server rack achieves effortless inspection, replacement and assemble
- Installation:wall mount network rack is easy to install,with instructions or videos for reference;Equipped with multiple accessories, suitable for different needs
- Application:EIA/ECA-310-E Compliant;wall mounted 4u rack fits all 19" racks and cabinets to hold various IT, network, and AV equipment;wall mount rack available in 4U, 6U, and 8U to choose
How power availability and location affect cost and schedule
A site’s electricity price matters, but the ability to secure power and connect to the grid can also determine when the facility can operate. Morgan Stanley Research reports that new-build AI data centers may take multiple years to reach power after construction begins. It quotes Lawrence Berkeley National Laboratory’s historical comparison: “projects built in 2022 took 5 years from the interconnection request to commercial operations, compared to 2 years in 2015 and <2 years in 2008.” This is a comparison of projects from those years, not a guaranteed schedule for a current project or a particular location.
The International Energy Agency reported in April 2026 that data-center electricity demand rose 17% in 2025, while worldwide electricity demand grew 3%. It identified grid connections and approvals, as well as supply constraints for transformers, gas turbines, advanced chips, and IT components, as bottlenecks to expansion. The IEA also reported that five large technology companies’ capital expenditure exceeded $400 billion in 2025 and was expected to rise a further 75% in 2026. These are sector-level indicators of scale and constraints, not a budget for an individual facility.
How to compare real project estimates
Before comparing two proposals, align the capacity and cost scope. A construction-only figure should not be compared directly with a turnkey deployment that includes GPUs, servers, and networking.
- Confirm whether capacity means IT nameplate capacity and whether both estimates use the same MW basis.
- Separate land, shell and core, utility works, cooling, and active IT equipment.
- Identify which party pays for technology fit-out and ongoing operations.
- Compare hardware configuration, network infrastructure, cooling design, and expected equipment replacement life.
- Check the site’s power price and reliability, interconnection plan and timing, and expected utilization.
- Include location-specific taxes, financing assumptions, and any differences in operating responsibility.
Company disclosures can illustrate execution risks without serving as neutral price benchmarks. For example, IREN’s fiscal 2026 filing lists data-center platform development and construction and GPU purchases among its primary cash requirements, and identifies risks including higher costs, falling GPU rental rates, counterparty exposure, and regulatory or sociopolitical conditions affecting development. Those risks are relevant context, but one company’s filing does not establish the cost of a typical AI data center.