1Clear out junk files and repair common Windows errors2Fix the driver behind crashes, sound loss and screen glitches3Repair Windows errors before they cause bigger problemsNot yet. Finland has proposed replacing arrival-order processing for many large electricity-consumption and storage connection requests with twice-yearly allocation rounds. Under the draft, most data centers above 1 MW would be handled in a capacity group, but they would not automatically be placed last: location, project readiness and certain voluntary commitments would affect ranking, and available capacity could allow a request to proceed without delay.
The proposal was still under consultation in the sources reviewed as of October 7, 2026. It should be described as a draft, not an enacted change.
As an Amazon Associate I earn from qualifying purchases.
What Finland has proposed changing
The Ministry of Economic Affairs and Employment has proposed an amendment to Finland’s Electricity Market Act (588/2013) covering consumption sites and energy-storage facilities, including requests to expand existing connections. It would apply across transmission, high-voltage distribution and ordinary distribution networks, but not closed distribution networks. Power-plant connections as such are outside the proposal; a mixed-use connection would be classified by its primary intended use. HPP Attorneys’ analysis of the draft describes the proposed categories and allocation rules.
Free tools Windows power users keep installed
One-click scans. No signup required.
Instead of processing every covered request as it arrives, the draft would retain year-round arrival-order processing for group 1 and handle groups 2–4 in batches twice a year. The first batch is proposed for no later than December 31, 2027. The change is therefore not a blanket end to first-come, first-served connections: it would create a different process for larger and other specified projects.
#1 Best Overall
- Double-Sided Battery Organizer: The Ontel Battery Daddy is a compact & portable way to organize, store and protect a boatload of batteries! Clear 'Easy View' cover lets you see everything at a glance and prevent any unwanted contact
- Maximize Battery Organization: Battery Daddy uses both sides to store up to 180 batteries of various sizes and types. This sleek, compact battery case holds 76 AA, 72 AAA, 8 9-Volt, 10 C, 12 Coin Cell and 8 D batteries (Batteries not included)
- Help Prevent Battery Drainage: Don't let loose batteries touch and drain other batteries. Stay organized and be prepared for power outages or battery-operated household items like remote controls, flashlights, toys and emergency gadgets
- Battery Tester Included: This battery storage case comes with a tester that can check whether your single-use or rechargeable batteries are still good. Align the battery's positive and negative ends on the tester to view the result on the indicator
- Durable and Portable Design: With a clear locking lid, secure latches, and a built-in carrying handle for easy portability and storage in many drawers, shelves or emergency kits. Great for professionals, technicians or anyone needing batteries on the go
Which group a data center would enter
The proposal sets separate thresholds for data centers alongside thresholds for other consumption sites. The relevant connection capacity determines the category; capacity is not the same as a project’s annual electricity use.
| Proposed group | Data-center threshold | Other covered cases described in the draft | Proposed handling |
|---|---|---|---|
| Group 1 | Up to 1 MW | Consumption sites up to 3 MW; critical consumption sites; specified small or co-located storage | Year-round processing in order of arrival |
| Group 2 | Above 1 MW through 10 MW | Other consumption sites from 3 MW through 100 MW | Twice-yearly batches; ranking would consider location and development stage, with qualifying voluntary commitments as a secondary criterion |
| Group 3 | Above 10 MW | Other consumption sites above 100 MW | Twice-yearly batches; ranking would consider location and development stage, with qualifying voluntary commitments as a secondary criterion |
| Group 4 | No separate data-center threshold stated | Other energy-storage facilities, as described in the draft | Twice-yearly batches |
These thresholds do not mean every request above 1 MW must wait for a batch: the draft’s categories would not apply where capacity is available to process a request without delay. In a constrained area, however, a data center above 1 MW would not retain the group 1 arrival-order process. If a group’s qualifying requests exceed the capacity available, the draft analysis says the remaining capacity would be allocated equally.
What could improve a larger project’s ranking
For group 2 or group 3 applicants, the draft would allow one or both of two voluntary commitments. They are distinct options with different thresholds and conditions.
Quick wins for a faster PC:
Clear out junk files and repair common Windows errorsFree Scan →Fix the driver behind crashes, sound loss and screen glitchesFind Drivers →Repair Windows errors before they cause bigger problemsFix Now →Flexibility commitment
An applicant could commit to make flexible generation or demand response available through an organized marketplace at a level of at least 10% of the site’s peak demand. For a group 3 data center, a commitment covering 80% of peak power would permit reclassification into group 2, according to HPP Attorneys’ account of the draft. The 80% figure is a separate threshold for group 3 data-center reclassification, not the general 10% flexibility requirement.
Rank #3
- Double-Sided Battery Organizer: The Ontel Battery Daddy is a compact & portable way to organize, store and protect a boatload of batteries! Clear 'Easy View' cover lets you see everything at a glance and prevent any unwanted contact
- Maximize Battery Organization: Battery Daddy uses both sides to store up to 180 batteries of various sizes and types. This sleek, compact battery case holds 76 AA, 72 AAA, 8 9-Volt, 10 C, 12 Coin Cell and 8 D batteries (Batteries not included)
- Help Prevent Battery Drainage: Don't let loose batteries touch and drain other batteries. Stay organized and be prepared for power outages or battery-operated household items like remote controls, flashlights, toys and emergency gadgets
- Battery Tester Included: This battery storage case comes with a tester that can check whether your single-use or rechargeable batteries are still good. Align the battery's positive and negative ends on the tester to view the result on the indicator
- Durable and Portable Design: With a clear locking lid, secure latches, and a built-in carrying handle for easy portability and storage in many drawers, shelves or emergency kits. Great for professionals, technicians or anyone needing batteries on the go
New-generation commitment
An applicant could commit to source at least 50% of the site’s estimated annual consumption from a new power plant. The plant would need to be commissioned no more than 36 months before the consumption site and located in the same transmission congestion area.
HPP Attorneys says these commitments would last for the connection’s lifespan. If a material failure remained unremedied, the operator could terminate the agreement; a new request for the same connection point could then be assigned to group 4 for five years. Those are draft terms, not final statutory requirements.
Rank #4
- 𝐊𝐞𝐞𝐩 𝐁𝐚𝐭𝐭𝐞𝐫𝐢𝐞𝐬 𝐎𝐫𝐠𝐚𝐧𝐢𝐳𝐞𝐝 𝐚𝐧𝐝 𝐑𝐞𝐚𝐝𝐲: Home-X battery storage organizer keeps your AA, AAA, C, D, and 9-Volt batteries neatly sorted in grooved slots, preventing rolling and ensuring easy access whenever you need fresh batteries.
- 𝐒𝐞𝐞-𝐓𝐡𝐫𝐨𝐮𝐠𝐡 𝐃𝐞𝐬𝐢𝐠𝐧 𝐟𝐨𝐫 𝐄𝐚𝐬𝐲 𝐕𝐢𝐬𝐢𝐛𝐢𝐥𝐢𝐭𝐲: Home-X's clear battery holder organizer allows you to instantly see what batteries are available, reducing clutter while keeping them clean, dry, and protected from dirt or moisture.
- 𝐌𝐮𝐥𝐭𝐢𝐩𝐮𝐫𝐩𝐨𝐬𝐞 𝐁𝐚𝐭𝐭𝐞𝐫𝐲 𝐒𝐭𝐨𝐫𝐚𝐠𝐞: Our battery case organizer features dedicated slots for each battery type, keeping up to 20 “AA", 16-24 “AAA”, 4 “D,” 5 “C” and 2 “9-Volt” batteries securely in place to avoid rolling and damage.
- 𝐒𝐩𝐚𝐜𝐞-𝐒𝐚𝐯𝐢𝐧𝐠 𝐰𝐢𝐭𝐡 𝐇𝐚𝐧𝐠𝐢𝐧𝐠 𝐋𝐨𝐨𝐩: Our slim, versatile battery storage box measures 10½"L x 6½"W x 1½"H, fitting easily into drawers or cabinets. Use the hanging loop to save space by storing it off the floor or tucked away.
- 𝐀𝐛𝐨𝐮𝐭 𝐇𝐨𝐦𝐞-𝐗: Home-X offers a wide range of products for the home or office. From gadgets for cleaning, cooking, and hosting to dinnerware and décor for any room, Home-X has something for everyone. Home-X is a registered trademark of Simply Home Solutions.
Why location and capacity matter
Finland does not have one uniform pool of grid capacity that guarantees access at any chosen site. Fingrid says available capacity depends on the connection location and other regional projects; connectivity and main-grid capacity are confirmed at the agreement stage. Its connection guidance calls for early technical discussions and says relevant planning and permits are required before a main-grid connection agreement. That makes grid access an early site-planning question, but does not establish how a particular application would rank under the proposal.
Fingrid reported in September 2025 that southern Finland faced grid-connection capacity shortages and that new transmission infrastructure was expected to increase capacity. It also reported several thousand megawatts of storage connection capacity elsewhere, particularly in Ostrobothnia and northern Finland. These are operator-reported conditions from 2025, not a current, site-specific capacity map.
Best Value
- Fireproof Explosion Proof Waterproof: Fireproof Battery Organizer Case is made of upgraded non-itchy silicone coated fiberglass that can withstand temperatures up to 2000. It's also highly water-resistant. And the special material has a certain explosion-proof performance, we design this Battery Organizer Box to minimize the hazards and losses caused by battery explosion
- Stores For More Type Batteries: It can hold 79*AA, 56*AAA, 8*C, 6*D, 9*9V, 30*Button type batteries( 3V lithium - CR 2032,CR 2016,CR 1632, CR 2025,LR44 etc.), total over 200 batteries. Keeping your batteries organized and helps extend the life of your batteries
- Safely Stores Batteries: Our fireproof battery organizer bag features a double zipper and durable handle to keep batteries from shock in the event that a defective battery were to swell, leak, or explode, our bag is designed to contain this and keep your family safe. This battery case neatly holds the batteries snugly in place within the foam pre-cut slots and keeps the contact ends from contacting each other, making it easy for you to find whatever battery
- Lightweight & Portable Battery Box Containers: You can not only hang the battery pouch on the wall, put it in a storage room or drawer and anywhere away from fire, but also take it with you on trips and to various outdoor activities. It is suitable for birthdays, New Year, Christmas, Valentine's Day, Mother's Day, Father's Day and many other holidays
- Please Note: BATTERIES NOT INCLUDED. YOHAWJER included a battery tester is suitable for all types of batteries with the organizer but Does NOT include any batteries. Super convenient for you to distinguish which batteries need to be recycled
Fingrid also reported more than 30,000 MW of energy-storage connection requests in September 2025—approximately twice Finland’s all-time peak electricity consumption—and said it had signed contracts for around 1,800 MW of grid-storage connections as of that month. These figures illustrate the scale of requests and contracted storage connections at that time; neither indicates how much capacity is now available to a particular data-center project. Fingrid’s September 2025 update gives the dated figures.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Status, proposed dates and existing requests
HPP Attorneys reports that the Ministry sent the draft amendment for consultation on September 18, 2026, with consultation closing October 9, 2026. Data Center Dynamics reports a proposed effective date of January 1, 2027, and a first allocation round in December 2027. The sources reviewed do not establish that the amendment has been enacted, so neither the effective date nor the allocation round should be treated as confirmed. Data Center Dynamics’ report describes the proposed timetable.
The draft could also reach requests made before its entry into force if no binding connection agreement had been concluded by then. A project with preparatory investments but no binding agreement could therefore face a different process if the proposal became law. The draft does not provide a site-by-site ranking or guarantee that a particular project will receive capacity.
What a data-center developer should assess
For a proposed site, the draft points to a practical set of questions—not a guaranteed route to a connection:
- Connection size: Is the request up to 1 MW, above 1 MW through 10 MW, or above 10 MW? The answer would determine the proposed data-center group unless a relevant reclassification applies.
- Local grid conditions: What capacity is available at the exact connection location, and what other regional projects affect it? Fingrid’s published figures are dated and cannot answer this for an individual site.
- Project readiness: How developed is the project? Location and development stage would inform ranking in groups 2 and 3.
- Commitment feasibility: Could the project meet the flexibility or new-generation conditions, including the relevant percentage, marketplace, timing and congestion-area requirements?
- Agreement status: Is there already a binding connection agreement? The draft’s proposed treatment of existing requests distinguishes those with an agreement from those without one.
- Network and approvals: Which operator and network level are involved, and are the technical discussions, planning and permits needed for the connection in progress?
HPP Attorneys also reports Fingrid’s forecast that data-center investments alone could increase Finland’s total electricity consumption by up to 40% over the next five years. This is an attributed forecast reported in 2026 legal analysis, not a measured increase or a guarantee of how demand will develop. It helps explain why the Ministry is proposing a more structured allocation process, but does not establish that all data centers will be delayed or denied connections.