DriversRecommendedOutdated drivers can make a good PC feel brokenScan driver issues before chasing fixes manually.Scan NowOctober DealsAmazon USOctober deal check: compare before you payAmazon US: current deals, useful picks and tech finds.Check DealsWindows FixRecommendedWindows errors stealing your time? Find the fix fastScan stability, cleanup and performance issues.Fix Now×
Skip to content
Agile

What Is a Burndown Chart? How to Read and Use One

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

A burndown chart is a graph of work remaining over time. Teams use it—most often during a sprint—to compare actual progress with a planned path and discuss whether the remaining work can be finished in the available time.

Time normally runs along the horizontal axis. The vertical axis measures remaining work in the team’s chosen unit, such as work items, story points, or hours. A planned “ideal” line is compared with an actual line based on the estimates and status of the work being tracked.

What a burndown chart shows

A typical chart starts with the total estimated work at the beginning of an iteration and trends toward zero by its planned end. The chart is a visualization of remaining work, not a complete account of everything happening in a project.

  • Horizontal axis: elapsed time, often the days in a sprint.
  • Vertical axis: remaining effort or work, measured with the team’s selected unit.
  • Ideal line: a planned guideline showing a steady path from the starting amount to zero.
  • Actual line: the remaining work calculated from recorded work-item status and estimates.

The unit matters. A chart measured in story points cannot be compared directly with one measured in hours, and a team should keep its estimation method consistent within the planning period.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
#1 Best Overall
Creative Safety Supply Project Planning Whiteboard (36in x 24in)
  • MAGNETIC DRY-ERASE SURFACE — The whiteboard design is permanently printed onto durable, industrial‑quality dry‑erase vinyl that won’t smudge and is resistant to stains and ghosting. Its smooth, long‑lasting writing surface is also magnetic, giving you added functionality for notes, magnets, and accessories
  • EASY INSTALLATION — Comes complete with durable mounting brackets and hardware, ensuring a secure and effortless wall‑mounting
  • DURABLE ALUMINUM FRAME — Built with a sleek 1" aluminum border and a spacious 2.5" deep aluminum tray to keep markers and accessories neatly within reach
  • SPACIOUS WRITING SURFACE — Ample writing space with a usable area that extends nearly edge‑to‑edge, measuring just 2" shy of the board’s total dimensions
  • Please inspect your whiteboard upon arrival — If you notice any issues, please contact us through Amazon's Buyer-Seller Messaging system

How to read the two lines

Actual work near the ideal line

When the actual line stays close to the guideline, progress is broadly tracking the plan. That does not prove that the sprint goal will be met, but it is a useful prompt for a quick status conversation.

Actual work above the ideal line

An actual line above the guideline means more work remains than the plan expected at that point. The sprint may be at risk, or the team may have added scope. Check the work items and the sprint goal before drawing a conclusion.

Actual work below the ideal line

A line below the guideline indicates that recorded remaining work is lower than the ideal path. It may reflect faster progress, smaller estimates, or an update to the work rather than a reliable prediction of early completion.

Rank #2
Lincia Acrylic Project Planning Board, 24 x 18 Inch Clear Wall Schedule Dry Erase Board with 8 Markers and Eraser, Whiteboard Planner with Lines for Home Office Project and Family Organization
  • Acrylic Material Complete Set: crafted from high transparency acrylic, this wall project planning whiteboard offers a sleek and sturdy surface for all your planning needs; The set includes a generously sized about 24 x 18 inches dry erase board, 8 colorful markers, and a practical eraser; Everything you need is included in one package
  • Smooth Writing, Effortless Erasing: the glossy acrylic surface of this acrylic project planning whiteboard ensures a smooth writing experience with no skipping or ghosting; Marks wipe away cleanly with the included eraser, leaving no residue behind; This reusable dry erase calendar maintains its clarity and functionality over repeated use
  • Versatile Use for Home Office: ideal for tracking projects, appointments, and family schedules, this acrylic wall schedule planner serves as a functional organizational tool; Its clear surface blends into any environment, making it suitable for offices, kitchens, home offices, or classrooms; It helps visualize deadlines and priorities clearly
  • Clear Print Long-lasting Design: the dates and headings on this dry erase planning whiteboard are printed with a heat sublimation technique, ensuring they remain smudge-proof and won't peel off over time; The acrylic wall calendar offers a crisp background that enhances readability while supporting written content
  • Thoughtful Functional Accessories: this acrylic project planning whiteboard set includes markers and eraser; The innovative magnetic pen holder and tray can easily attach to the calendar surface; These accessories help keep your writing tools organized and prevent them from getting lost

A sudden step down

A sharp drop can occur when several items are completed or estimates are updated in a batch. It is a signal to investigate how the data was entered; it is not, by itself, evidence of a sudden change in productivity.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

What a burndown chart can—and cannot—tell you

Use the chart to support a short progress and forecasting discussion. It can reveal that remaining work is not declining as planned and help the team decide whether to clarify scope, remove impediments, or revise its forecast.

It cannot independently explain why work is late, show whether the delivered work is high quality, measure customer value, or guarantee that the sprint goal will be achieved. The chart also does not provide a fair stand-alone assessment of an individual or team. Interpret it with the sprint goal, work-item details, and the team’s conversation.

Rank #3
Creative Safety Supply Project Planning Whiteboard (48in x 36in)
  • MAGNETIC DRY-ERASE SURFACE — The whiteboard design is permanently printed onto durable, industrial‑quality dry‑erase vinyl that won’t smudge and is resistant to stains and ghosting. Its smooth, long‑lasting writing surface is also magnetic, giving you added functionality for notes, magnets, and accessories
  • EASY INSTALLATION — Comes complete with durable mounting brackets and hardware, ensuring a secure and effortless wall‑mounting
  • DURABLE ALUMINUM FRAME — Built with a sleek 1" aluminum border and a spacious 2.5" deep aluminum tray to keep markers and accessories neatly within reach
  • SPACIOUS WRITING SURFACE — Ample writing space with a usable area that extends nearly edge‑to‑edge, measuring just 2" shy of the board’s total dimensions
  • Please inspect your whiteboard upon arrival — If you notice any issues, please contact us through Amazon's Buyer-Seller Messaging system

Common types of burndown chart

Type Planning horizon Best use Important consideration
Sprint burndown One iteration or sprint Monitor remaining work against the sprint plan Useful for short-cycle conversations; changes to sprint scope can distort the line.
Epic burndown A larger body of related work Track progress toward completing an epic Requires estimates and status that remain meaningful across multiple iterations.
Release or version burndown A planned release or version Discuss whether the remaining work fits the release timeframe Longer horizons increase the effect of changing scope and estimates.

Choose the horizon that matches the decision being made. For frequent scope changes, a burnup chart may be clearer because it separates completed work from the total amount of scope.

Burndown versus burnup

A burndown emphasizes what remains. A burnup chart usually plots completed work and a total-scope line, making additions or removals of scope easier to see. If the main question is “How much is left?”, a burndown may be the simpler view. If the question is “What changed in the total commitment, and how much has been completed?”, a burnup often communicates that more clearly.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

How teams use one during a sprint

  1. Set the starting point. Add the sprint’s selected work and estimates before or at the start of the iteration.
  2. Record work consistently. Update item status and remaining estimates using the team’s agreed rules.
  3. Review the chart with context. Compare the actual line with the ideal line, then inspect blocked items, newly added work, and estimate changes.
  4. Act on the discussion. Resolve an impediment, clarify an acceptance condition, negotiate scope, or revise the forecast when the evidence supports it.
  5. Inspect the outcome. At the end of the sprint, compare the result with the sprint goal and what was actually delivered, rather than judging success from the line alone.

Using a digital tool such as Jira

Jira provides a burndown report for Scrum boards that tracks remaining sprint work. The exact calculation and display depend on the board’s configuration, issue estimates, and status updates, so a Jira report should be treated as an implementation of the general concept rather than a universal definition of every burndown chart.

Rank #4
Large Visual Project Management Board,36"x45"
  • DRY ERASE PROJECT MANAGEMENT PLANNER: Be made of 250 gsm construction paper, laminated by special formula film that is erasable, make the surface resistant to ghosting or staining. We can erase easily even months later and use this work schedule board over and over again
  • PRODUCTIVE PROJECT MANAGEMENT TOOLS: This project management board is a game changer and something physical for managing personal or team projects efficiently. It allows you or members to quickly view and share the status of up to 12 projects at the same time, a very good practical kit of team building
  • SCRUM WHITEBOARD FOR OFFICE ESSENTIALS: This project organizer worth the investment for business use. It's easy to use for products development, marketing strategic projects or as a sales goal tracking whiteboard. You can easily measure budget, milestones, resources, inventory and timeline at a glance. It helps you plan, execute, assign tasks efficiently
  • MOUNTING IS A BREEZE: This vision board is lightweight and comes with removable mounting stickers. You can mount this program Management Board easily without tools. On the other hand, you can take it down easily too if you need to remount your project board to other place later
  • COMPLETE ACCESSORIES INCLUDED: Our huge project manager planner for wall is cost-efficient for daily use in office, home office or family. It comes rolled in a study tube with, premium dry erase eraser, reusable fluorescent colored tabs for entrepreneurs, managers or person working at home

Before relying on a digital chart, verify which issues are included, which estimation field is used, how completed work is recorded, and whether scope can be added after the sprint begins. A chart can look precise while reflecting incomplete or inconsistently updated data.

Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Support on Ko-Fi

Common interpretation mistakes

Treating the ideal line as a performance target

The ideal line is a planning aid, not a productivity quota. Real work rarely decreases at a perfectly even rate, and forcing the line can encourage premature status changes or distorted estimates.

Assuming a late line proves poor execution

More remaining work can result from added scope, clarified requirements, re-estimation, or blocked work. Inspect those possibilities before attributing a cause.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.
Best Value
Creative Safety Supply Project Planning Portrait Whiteboard (36" x 24")
  • MAGNETIC DRY-ERASE SURFACE — Designs are directly printed onto a durable vinyl layer that is resistant to stains and ghosting, ensuring long-lasting visibility and a smooth writing surface. The surface is also magnetic, giving you freedom to accessorize your whiteboard however you like or attach any number of documents
  • EASY INSTALLATION — Includes mounting brackets and hardware for secure and hassle-free wall mounting. For a quick tutorial on how to properly install your whiteboard, please watch our video located in this product page
  • SPACIOUS WRITING AREA – Large enough to capture a wide range of information without running out of space, encouraging collaboration and communication between departments. Writing area measures 2" less than the board's total dimensions
  • DURABLE ALUMINUM FRAME – 1" aluminum border paired with a 2.5" deep aluminum tray for convenient accessory storage
  • Please inspect your whiteboard upon arrival – If you notice any issues, please contact us through Amazon's Buyer-Seller Messaging system

Confusing completed tasks with delivered value

Closing many small items does not necessarily mean that the most valuable part of the sprint goal is complete. Pair the chart with prioritization and outcome information.

Ignoring data quality

Stale statuses, missing estimates, and batch updates can make the trend misleading. Consistent definitions and updates are prerequisites for a useful chart.

Is a burndown chart required by Scrum?

No. Scrum Alliance describes a burndown chart as an optional tool, not a formal Scrum artifact. A team may use one when it improves transparency and conversation, or choose another way to inspect progress toward its goal.

When to choose another view

  • Choose a burnup when changing scope must be visible.
  • Use a cumulative-flow diagram when the key issue is work moving through workflow states and possible bottlenecks.
  • Use a task board and sprint-goal discussion when item-level blockers matter more than a numerical trend.
  • Use delivery and outcome measures when stakeholders need evidence of value, quality, or customer impact rather than remaining effort.

Practical checklist

  • Is the time period clearly defined?
  • Is the vertical-axis unit understood by everyone viewing the chart?
  • Are estimates and statuses updated consistently?
  • Can the team identify scope added or removed during the period?
  • Are blocked items and the sprint goal discussed alongside the graph?
  • Is the chart being used for shared inspection rather than individual performance ranking?

Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Leave a Reply

Your email address will not be published. Required fields are marked *

Special offer. See more information about Outbyte and uninstall instructions. Please review EULA and Privacy policy.

Read next

Recommended PC Tool
Recommended PC Tool
Windows Errors? Fix Them Before They SpreadFree repair scan
Crashes, No Sound, or Screen Glitches?Free driver scan

Two free Windows tools

One Free Minute Could Fix That PC

Before you go - each of these free tools takes about a minute and tackles what quietly slows a Windows PC down.

Special offer. View Outbyte info, uninstall instructions, EULA, and Privacy Policy.