Pure Data Centres Group has completed installation of the third and final transformer at its 90MW LON01 data-centre campus in Brent Cross, North London. The 75MVA Hitachi transformer lifts the substation’s total installed capacity to 150MVA. Energisation was planned for later in October 2026, but the milestone does not mean the wider campus is complete: the LON01B2 expansion remains under construction and is scheduled for completion in the second quarter of 2029.
What Pure DC installed
The new unit is a 75MVA Hitachi power transformer, the final of three transformers serving the LON01 campus. Once energised, it will complete the dedicated power system designed for the site and bring the substation’s total capacity to 150MVA.
As an Amazon Associate I earn from qualifying purchases.
Transformer capacity is expressed in megavolt-amperes (MVA), an apparent-power rating used for electrical infrastructure. The campus itself is described in megawatts (MW), a measure of real power available to its computing and cooling systems. The two figures are related but are not interchangeable; the 150MVA substation rating does not mean the campus suddenly becomes a 150MW facility.
Do these 3 things before closing this tab:
1Fix the driver behind crashes, sound loss and screen glitches2Repair Windows errors before they cause bigger problems3Scan for outdated or missing drivers - takes under a minuteWhy the lift required a specialist gantry
The installation took place beside a live substation and within a restricted operational campus. That geometry ruled out the conventional 500-tonne crane normally considered for a transformer of this type.
#1 Best Overall
- 220V to 110V Converter: The first pure sine wave voltage converter! Converts 220-250V down to a stable 120V pure sine wave, Suitable for any American appliances with 110-120V and power ranging from 0-1600 watts. Such as CPAP machines, hair straighteners, curling irons, hair dryers, coffee makers, blenders, electric toothbrushes, and more.
- International Power Adapter Converter Combo: Includes 4 types of international power adapters - Type C, Type G, Type I, Type E/F plugs compatible with outlets in Europe, Israel, UK, Spain, Italy, France, China, Australia, Iceland, Ireland, and Asia, suitable for use in over 160 countries.
- Advanced Safety Features: This 220V to 110V Converter is equipped with multiple safety mechanisms, including Over-Temperature Protection, Over-Current Protection, Overload Protection, Surge Protection, and Short Circuit Protection, this voltage converter provides a secure operation environment for all connected devices. Additionally, it has passed CE safety certification and UL safety testing.
- Intelligent Protection: Automatically disconnects power and flashes its indicator light if any issue is detected. A simple restart resumes normal function. Compared to traditional systems where fuses need to be manually replaced, a fuseless design offers a more convenient and reliable form of protection.
- 100% Satisfaction: The HYTED 1600Watts 220V to 110V Converter International Power Adapter Combo is backed by a reliable 24-month warranty and supported by a team of friendly customer service professionals. For any inquiries, please email us, and our technical representative will respond within 12 hours.
Instead, the project team designed and deployed a specialist gantry rated to lift up to 1,000 tonnes. Pure DC, MGE Group, logistics partners and specialist suppliers completed the move into position in a four-hour operation. The method allowed the transformer to be placed without taking the surrounding live infrastructure out of service or requiring the clearance that a large mobile crane would have needed.
From Colombian manufacture to Brent Cross
The transformer’s delivery was an 18-month programme rather than a short on-site installation. Manufacturing began in Colombia in March 2025, and factory testing finished in June 2026. The unit then travelled by sea to the United Kingdom before making its final journey to the Brent Cross campus.
Rank #2
- 【3000w 110V/120V to 220/240V】2 US standard sockets for 110-120V appliance; 2 universal sockets accept all types of plugs except the big south African plug for 220-240V appliance.【For optimal use】 For optimal use, it's recommended to use a Voltage Converter that's max watts is at least 50% higher than your appliance without a motor.
- 【As a step-up transformer】 The input voltage behind the unit is selected as "110V", which converts the local voltage of 110V/120V in the United States, Canada, Mexico, etc. to 220V/230V/240V to support the use of 220V-240V electrical appliances from China, Australia, the United Kingdom, Germany, Italy, and other countries.
- 【As a step-down transformer】 The input voltage behind the unit is selected as "230V", which converts the local voltage of 220V/230V/240V in the China, Australia, UK, Germany, Italy and other countries. to 110V/120V to support the use of 110V-120V electrical appliances from United States, Canada, Mexico, etc.【NOTE】The transformer is equipped with an US power cord, if used in other 220V-240V country you MUST need a plug adapter.
- 【AC Input】Equipped with an US Power Cord.Features a universal power wiring slot, allowing you to purchase a separate power cord tailored to the outlet specifications of different countries for easy connection and usage.
- 【Resettable Circuit Breaker 】No need to replace fuses any more.Kindly notice that when overloaded,it will pop out autoatially. You only need to press to reset in a few seconds and continue to use the transformer.
That last leg required route planning, road closures and approvals from local authorities. Large transformers are unusually difficult road loads because of their weight, dimensions and handling limits, so the route and lifting plan had to be coordinated with the campus construction schedule and the operating substation.
What the transformer enables at LON01
The transformer supports the campus’s B1 and B2 buildings. Dedicated ductwork for B2 is already in place, linking the electrical infrastructure milestone to the next stage of the development rather than marking the end of construction.
Rank #3
- Primary Voltage: 120/208/240 V AC ,
- Secondary Voltage: 24 V AC
- Power Rating:40 VA
- Compatibility: Transformers can be used in industrial, heating and air conditioning controls including air conditioning circuits, relays and gas valves or other applications up to the listed ratings
- Directly tested with a multimeter is no-load voltage: AC26.6V-27.5V
LON01 is being developed as a closed-loop, liquid-cooled data centre for high-density artificial-intelligence inference and cloud workloads. Liquid cooling is intended for equipment whose heat output can exceed what conventional room-air cooling can efficiently remove. The completed power train will therefore be an enabling part of the high-density design, while the buildings, internal systems and commissioning work still have to progress.
Independent reader supportYour contribution helps us test, update, and keep practical guides available for everyone.Where the Brent Cross expansion stands
LON01B2 is described by Pure DC as the final major build phase at Brent Cross. The project adds 70MW and more than 23,000 square metres, taking the overall campus capacity to 90MW. Completion is scheduled for Q2 2029.
Rank #4
- Worldwide Use: It equipped 5 different sockets for (UK, US, AU, IN, EU); voltage converts 220/240V to 110/120V so you could use American electronics in Antigua & Barbuda, Aruba, Bulgaria, Cambodia, Canada, China, Costa Rica, Dubai, England, Fiji, Germany, Guam, Haiti, Hong Kong, Ireland, Japan, North Korea, South Korea, Malaysia, New Zealand, Peru, Puerto Rico, Singapore, Turkey, United Kingdom and more.
- Patented Product with Patent Number: US10270355B1, it has new features which works perfectly for hair straightener flat iron, Curling Wand, electric shaver, beard trimmer, hair clippers, laptop, breast pump, CPAP, electric toothbrush, nebulizer, Xbox, tablet, kindle, TV, DVD players, Bluetooth speaker, camera batteries and so on.
- 4 USB Ports: With a type C port PD 18W and 3 usb-a ports feature all mobiles for Galaxy S10 / S20 / S21 / S22, Note 9 / 10/ 20, Nexus 6 and HTC combines capable of simultaneously charging multiple power-hungry devices for iPhone, iPad, android and tablets.
- Safety and Protections: Over-current, over temperature, short-circuit and overload. Note: USB outputs are completely isolated from the AC power to keep your devices safely.
- Friendly Reminder: Do Not Use with Hair Dryers, Tools and other Household Appliances over 230 watts.
Construction and fit-out are continuing inside a live operational campus, alongside existing infrastructure. That constraint affects sequencing, access, safety controls and temporary works: new equipment must be installed without disrupting systems already supporting operations.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
| Project element | Reported figure or status |
|---|---|
| Campus capacity after the expansion | 90MW |
| Final transformer | 75MVA Hitachi unit |
| Total substation capacity after installation | 150MVA |
| Specialist lifting equipment | 1,000-tonne-capacity gantry |
| Transformer positioning time | Four hours |
| LON01B2 expansion | 70MW and more than 23,000 square metres |
| Scheduled B2 completion | Q2 2029 |
Environmental plans for B2
After B2 is complete, the site is planned to include a living wall wrapping around the building with more than 750,000 plants. Pure DC says the feature is intended to reduce noise and air pollution and support biodiversity beside Brent Reservoir’s Site of Special Scientific Interest.
The living wall is a planned element of the completed development, not a benefit delivered by the transformer installation itself. Its eventual performance will depend on the final design, planting and long-term maintenance of the system.
Quick Recap
What happens next
- Energisation: The newly installed transformer was planned to be energised later in October 2026, subject to the project’s commissioning and safety procedures.
- Building construction: Work on the LON01B2 structures and associated services continues within the operating campus.
- Fit-out and commissioning: Electrical distribution, liquid-cooling systems and data-centre equipment must be installed, tested and commissioned before the expansion can support workloads.
- Target completion: Pure DC’s stated schedule places completion of the B2 phase in Q2 2029.
Product prices and availability are accurate as of the date/time indicated and are subject to change. Any price and availability information displayed on Amazon at the time of purchase will apply.