Canada is building toward its first small modular reactor, but only one project has crossed into licensed construction: Ontario Power Generation’s Darlington unit. Saskatchewan is funded for studies, not yet committed to construction. The national strategy is therefore a staged bet—real progress on licensing and design, with financing, waste, fuel, Indigenous participation and operating approval still unresolved.
What Canada is actually building
The clearest answer to “Is Canada building an SMR?” is yes, at Darlington in Ontario—but construction authorization is not the same as permission to operate. The Canadian Nuclear Safety Commission (CNSC) issued Ontario Power Generation (OPG) a construction licence for one GE Hitachi BWRX-300 reactor. OPG would need a separate operating-licence hearing and Commission decision before loading fuel or generating electricity.
As an Amazon Associate I earn from qualifying purchases.
The BWRX-300 is a boiling-water reactor design rated at about 300 megawatts (MW). Darlington’s existing nuclear site could eventually accommodate four new reactors. The federal government has also committed funding for a next phase involving three additional BWRX-300 units, but those units are not covered by the licence for the first reactor.
Darlington: Canada’s reference project
Design selection and licensing
OPG selected the BWRX-300 in December 2021 and applied for a construction licence in October 2022. In April 2025, the CNSC issued construction licence PRCL 32.00/2035 for one unit, valid until March 31, 2035.
#1 Best Overall
- [Ultra-Lightweight Ear Buds Designed for Small Ears] Each earbud weighs only 3.7g and features a compact, ergonomic in-ear design made especially for small ears. Secure, low-profile, and comfortable for workouts, all-day wear or overnight sleeping.The ultra-slim profile sits flush in your ear with no hard edges poking or rubbing, so you can even sleep on your side without discomfort.
- [Immersive Stereo Sound with TOZO OrigX Technology] TOZO OrigX tuning delivers clear vocals, balanced mids, and natural stereo sound for music, podcasts, and videos.
- [Long Battery Life for Daily Use] Get up to 7 hours of playtime on a single charge, with up to 32 hours total using the charging case—ideal for workdays, commuting, and extended listening sessions.
- [Bluetooth 5.3 & Stable Connection] Bluetooth 5.3 provides fast pairing, stable wireless performance, and reduced dropouts as you move around home or office.
- [Deep Bass with Clear Vocals] High-performance drivers produce punchy bass while keeping vocals clean and detailed for everyday listening.
The licence contains environmental follow-up requirements, regulatory hold points and conditions for Indigenous engagement. It permits construction activities defined by the licence; it does not authorize operation. The CNSC has explicitly said that operating authorization would require a future application, public hearing and decision if OPG proceeds to that stage.
Planned fleet size and federal funding
The Darlington site is proposed for up to four reactors. A March 2025 federal announcement committed $55 million to advance three additional BWRX-300 units. At roughly 300 MW each, those three units would total about 900 MW. The government estimates that amount could serve approximately 900,000 homes; that is an official estimate, not a measured output from operating reactors.
No published evidence in the current record establishes Darlington’s final all-in construction cost, levelized electricity cost or commercial operating date. Older strategy documents that mention 2028 should not be treated as current commitments in light of the newer licensing and funding decisions.
PC Slower Than It Used to Be?
A free scan shows the junk files, broken settings and background clutter dragging Windows down - then fixes them in one click.Free scan · Windows 10 & 11Outdated Drivers Are Slowing You Down
One free scan finds every outdated or missing driver and matches the right update for your exact hardware.Free scan · exact hardware matchRank #2
- 【IP68 Waterproof Multifunctinal Smart Watch】Torjalph fitness activity tracker smart watch is IP68 waterproof technology ,you can wear it when swimming,handwashing,it's rain-proof which means that you perform multiple exercise modes outside without worrying about sweat or rain corroding your fitness smart watch,and this watch equipped with a 230 mAh large capacity battery magnetic charging ,and this sports activity tracker watch can be used 5-7 days If fully charged.
- 【Larger 1.83'' Full Screen Watch & Multi-dial Selection】1.83 inch full HD color touch screen smart watch for men / women provides excellent 240*284 resolution image quality ,This Bluetooth smart watch offers a better touch experience and remarkable immersion and ,more than 200 watch faces for you to choose from App"Da Fit ", you can change the dial style according to your mood to wear keeping the world on your wrist
- 【Accurate Activity Tracker Smart Watch 】sports watch activity tracker uses sweat and dust resistant breathable silicone strap, our Fitness Tracker Smart Watch for Android iOS Phones supports 12 sports modes,walking,running,bicycle,swimming,badminton,basketball,football,rope skipping. This bluetooth calls smart watch for men women is lightweight and stylish, bringing more convenient and relaxing sports experience while also providing more protection.
- 【Your 24 Hour Personal Daily Health Monitor】Fitness watch for women men full touch screen IP67 waterproof bluetooth smartwatch for Android iOS Phones with heart rate blood pressure monitor multifunction Andriod smart watch with steps counter sleep monitor sports fitness watch, monitoring blood oxygen saturation allows you to understand your physical condition in real time to track fitness progress ,to know your health status in time.
- 【More Functions Bluetooth Call Smart Watch】This fitness activity smart watch full screen for iPhone and Android phones includes a bunch of new features including:The bluetooth smart watch can hang up the phone, receive and display WhatsAPP /Text /Facebook /Twitter /Messenger reminder.Support sedentary reminder, alarm clock, stopwatch, timer,weather information,music control, remote camera control compatible with Android 5.0 and above or iOS 9.0 and above smartphones.
Saskatchewan: funded development, no build decision yet
What has been decided
SaskPower selected the BWRX-300 for potential deployment in the mid-2030s. Natural Resources Canada (NRCan) announced up to $74 million in federal support for pre-engineering, technical studies, environmental and regulatory work, and community and Indigenous engagement.
The key word is “potential.” SaskPower and the federal government expect a decision on whether to build in 2029. Until that decision, Saskatchewan remains in pre-development rather than licensed construction.
Economic projections—and their limits
For a possible 1,200-MW Saskatchewan build-out, a Conference Board of Canada study commissioned by SaskPower and OPG and cited by NRCan projected approximately 1,700 direct and indirect jobs. The same study projected an $8.8 billion increase in gross domestic product, $5.6 billion in wages and $2.9 billion in tax revenue over the facilities’ 60-year lifespan. These are modeled economic projections, not results already delivered by a plant.
Rank #3
- [Low Noise High Fidelity] New bee guitar cord with 22AWG oxygen-free-copper center conductors provides enhanced signal transfer, the PVC insulation material and the high-density stranded copper double shield provide noise rejection for quiet operation
- [Ideal for Choice] New bee 1/4 straight and right angle metal connectors, ensures a secure connection in any instrument, pedal, or amp jack. L shape great fro on stage guitar stands
- [Wide Compatible] Suitable for mixer, power amplifier, microphone, effector, decoder, equalizer, electoronic organ, electric guitar, electric bass and other electronic equipments. Widely used in the installation of smart home, karaoke speaker, professional stage audio, etc
- [Easy Disassemble] Making incidental repairs quick and easy! Very nice, flexible cable
- [Dont Hesite to Order] 24 hours customer services and professional technology team are standing by
How the two projects compare
| Project | Reactor design | Current regulatory stage | Capacity described | Decision or timing | Funding and cost information |
|---|---|---|---|---|---|
| Darlington, Ontario | BWRX-300 | Construction licence for one unit; operating licence not issued | One unit about 300 MW; site proposed for up to four; three additional units described as about 900 MW total | Construction licence valid to March 31, 2035; operating date not established | $55 million federal commitment for work on three additional units; final construction and generation costs not stated |
| Saskatchewan | BWRX-300 selected for potential deployment | Pre-engineering and studies; no construction licence | Potential 1,200-MW build-out in economic modeling | Potential mid-2030s deployment; build decision expected in 2029 | Up to $74 million federal development support; modeled economic benefits, not realized returns |
Why Ottawa and the provinces are betting on SMRs
Canada’s 2020 SMR action plan presents the technology as a possible source of non-emitting electricity for large grids, heavy industry and remote communities. The policy case is not limited to selling reactors: governments also see opportunities for Canadian engineering, manufacturing, uranium and nuclear-service supply chains.
The Tool Desk
Outbyte Driver Updater FREEFix the driver behind crashes, sound loss and screen glitchesFind Drivers →Outbyte PC Repair FREEClear out junk files and repair common Windows errorsFree Scan →The action plan describes a potential global SMR market estimated by the federal government at $150 billion per year by 2040. That figure is a government-cited projection, not a guaranteed market size or revenue forecast for Canada.
NRCan’s later roadmap was developed with provinces, utilities, Indigenous and northern stakeholders and industry. It contains more than 50 recommendations covering regulatory readiness, waste, international engagement and public participation. The roadmap treats those areas as implementation requirements, not optional add-ons.
Rank #4
- Digital Family Calendar: BSIMB digital calendar wall touch screen puts an end to your chaotic life. Designed for busy families, the digital calendar keeps you organised and in step with your family. Assign different colours and tasks to each family member to make family scheduling easier and more intuitive.
- Easy Setup and Auto-Sync: Plug in, connect to WLAN and auto-syn your electric calendar in minutes. Digital wall calendar compatible with Google calendar, iCloud calendar, Outlook calendar, Cozi calendar and Yahoo calendar. Add events directly on the device or through the ecalendar app. Electronic calendar stays current whether you're at work or traveling—no manual updates needed.
- All-In-One Home Assistant: Smart calendar builds habits and encourage independence with personalised chores. Display daily meal plan to reduce the daily ‘What's for dinner?’ stress. To-do lists keep track of everything you want. Turning chores into valuable achievements with stars and rewards, making life easier and more enjoyable.
- Manage Anytime Anywhere: BSIMB electronic calendar for family stay connected with the powerful ecalendar app. Access and manage your digital wall calendar anytime, anywhere with free features like stars & rewards, photo screensaver, chore charts, meals plans, to-do lists etc. Electronic planner paid features like Magic Import tailor advanced tools for users with special needs.
- Stay in Touch with Loved Ones: Share photos or videos from your phone to electronic wall calendar with app, instantly update your life moment, and keep in touch with your family, especially those who are far away; you can also surprise your smart calendar digital wall by sending him a wish card; it's also great for keeping tech-illiterate elders in touch with the youngsters.
The issues that will determine whether this becomes a fleet
Licensing and construction risk
Darlington’s licence demonstrates that a BWRX-300 can reach a Canadian construction decision, but every additional unit still faces project approvals, hold points and oversight. A construction licence does not settle the requirements for commissioning, emergency planning or operation.
Affordability and financing
Small reactors may be easier to add in increments than a single very large plant, but smaller electrical output does not automatically mean lower total cost per megawatt. Final capital costs, financing terms, schedule performance and the price of electricity will determine whether utilities can repeat the design. Those figures have not been established for Darlington in the available announcements.
Fuel, transport and supply chains
A commercial fleet needs dependable fuel fabrication, component manufacturing, transportation routes and qualified workers. Canada’s roadmap specifically identifies fuel and transport as issues requiring implementation work. A first reactor can rely on project-specific arrangements; a fleet needs standardized, repeatable logistics.
Best Value
Used fuel, waste and decommissioning
SMRs still produce radioactive used fuel and require plans for storage, transport, eventual disposal and decommissioning. The federal roadmap identifies waste management as a central issue. “Small modular” describes the reactor concept and potential construction approach; it does not eliminate the waste obligations of nuclear power.
Indigenous rights and public confidence
Darlington’s licence includes Indigenous-engagement conditions, while Saskatchewan’s federal support includes community and Indigenous engagement. Consultation, participation and—where communities seek it—ownership or economic partnership will affect project legitimacy and timelines. Public confidence also depends on transparent emergency planning and evidence that regulators can enforce licence conditions.
What happens next
- Darlington must execute the licensed construction work. OPG will have to meet the licence’s environmental, engagement and regulatory hold-point conditions.
- OPG would then need an operating licence. The CNSC would review a future application in a public hearing before the reactor could operate.
- The three-unit expansion must move from funding to project decisions. The $55 million commitment advances work; it is not an operating authorization or a final cost approval.
- Saskatchewan must complete its studies and decide in 2029. The decision will weigh system needs, costs, regulation, waste, fuel, community and Indigenous participation, and construction readiness.
- Canada must prove repeatability. A successful first unit would need to be followed by predictable schedules, financing, supply chains and waste arrangements before “fleet” becomes more than a policy goal.
Why the bet matters now
Energy Minister Tim Hodgson said at the 2026 Nuclear Energy Strategy launch that Ontario’s project “will make Canada the first country in the G7 to deploy a small modular reactor.” That is a policy statement about the intended outcome, not evidence that an operating reactor already exists. The measurable milestone today is narrower: Canada has one SMR construction licence at Darlington, while Saskatchewan is preparing for a 2029 build decision.
Recommended Free Tools
That distinction captures Canada’s position. The country has moved beyond a paper strategy, but it has not yet demonstrated an operating SMR, a final project price or a repeatable national build program. Licensing, economics, waste management, fuel, Indigenous participation and public trust will decide whether the first project becomes a durable fleet.