Bell has announced plans for up to 900 megawatts (MW) of additional capacity at its Regina-area AI data-centre project, but the available official announcements do not confirm a purchase of nearly 900 acres. The figure refers to power capacity, not land area. Bell says it owns the current site and describes two adjacent agricultural parcels as available for future development.
What Bell and Saskatchewan have announced
Bell announced a 300 MW AI data centre in the Rural Municipality of Sherwood, just outside Regina, on March 16, 2026. On September 14, Bell and the Government of Saskatchewan announced a non-binding memorandum of understanding (MOU) for phased development of up to 900 MW of additional capacity. If the proposed expansion goes ahead, the provincial hub would total up to 1.2 gigawatts (GW).
As an Amazon Associate I earn from qualifying purchases.
The distinction matters: 900 MW is a measure of electrical power capacity. It is not a statement that Bell is buying 900 acres. The official project announcements and Bell’s site material cited here do not verify a purchase agreement for nearly 900 acres.
Free tools Windows power users keep installed
One-click scans. No signup required.
What is known about the land
Bell’s site brochure says the existing site is fully owned by Bell and identifies two adjacent agricultural parcels as available for future data-centre development. That description indicates land that could support future development; it does not establish that Bell has bought those parcels or intends to buy nearly 900 acres.
#1 Best Overall
Without a land-title record, municipal record or later official announcement confirming a transaction, the acreage and purchase claim remains unverified. Land area and power capacity should not be treated as interchangeable just because both figures are associated with the expansion.
How the proposed expansion differs from the initial campus
| Project element | Initial campus | Proposed expansion |
|---|---|---|
| Announced capacity | Up to 300 MW | Up to 900 MW additional, potentially bringing the provincial hub to 1.2 GW total |
| Status | Construction was underway in the October 1, 2026 update | Phased development under a non-binding MOU; conditional on further commitments and approvals |
| Power supply | Provincial-grid power | Proposed bring-your-own-power approach, with partner-developed natural-gas generation |
The proposed additional capacity depends on customer commitments, commercial agreements, permits, approvals and relevant environmental assessments. The MOU is not evidence that the full 900 MW is already built, approved or operating.
Rank #2
What the construction update does—and does not—show
In an October 1, 2026 update, Saskatchewan said structural steel was rising, all four first-phase buildings were taking shape and more than 500 people were working on site. Those details describe construction of the initial campus. They do not mean the proposed additional 900 MW has been completed.
What’s actually slowing this PC down?
Pick the symptom - the matching free tool is one click away.
Investment and jobs are projections, not completed results
Government announcements attach large projected figures to the plan, but they should be read as estimates rather than outcomes already delivered. Innovation, Science and Economic Development Canada described planned capital investment of up to $52.5 billion and estimated up to 4,500 jobs overall. Saskatchewan estimated up to 500 permanent jobs associated with data-centre operations and power generation, plus an estimated 3,000 additional jobs in security, logistics and maintenance.
These figures relate to the announced plan and its projections. They are not current employment counts or proof that the proposed expansion has been completed.